Case study 31 Day St, Leichhardt Value Management

Same home.
$150K less to build.

The plans were complete when this client came to us. A slight redesign of the structure brought the build cost down by $150,000.
Before
$870K
Our estimate on the original plans, with structural steel beams
After
$720K
After Value Management, redesigned with timber beams
01
Plans complete
The design was fully documented when it came to us for pricing. Our estimate on the plans as drawn was $870,000.
02
Repositioning the stairs
Working with the engineer, we redesigned the stairs to sit on a load-bearing wall. This removed the need for structural steel and kept a solid foundation, with timber beams used instead.
03
A $150,000 saving
A slight redesign brought the price to $720,000, confirmed before construction began.
★★★★★  Google review
“This is our 2nd major renovation, and I have to say we’re lucky we had Michael from Protabuild. We wanted to work with someone who was flexible and could work with us to build our home and Michael certainly accomplished that. He was happy to hear our ideas and helped provide different options according to our budget and needs. You know your house is well built when you have other trades commenting on the quality of the build! Really happy with the end result, would happily build with Michael again.”
Brendon Davies · Leichhardt
Have plans ready? Talk to us before you build.
The earlier we are involved, the more of your budget and your design we can protect.
Start your enquiry Case study (PDF)
Value Management

A smarter way to build, from concept to completion

Bringing your builder into the design process early, so your home is designed against real construction costs. Rather than waiting until your plans are complete before discussing costs and buildability, important decisions are reviewed and refined throughout the design process.

01Stage one

Project Assessment & Feasibility

  • Review your concept and design direction
  • Discuss priorities, budget and objectives
  • Assess the site and documentation
  • Identify opportunities and challenges
02Stage two

Value Management

  • Review plans and construction details
  • Assess buildability and methodology
  • Ongoing budget guidance and alternatives
  • Support informed design decisions
03Stage three

Construction Readiness

  • Review documentation and consultant info
  • Finalise details and confirm scope
  • Prepare the project for construction
  • Confirm what will be built
Value Management Plan (PDF)